We are in construction mode full swing this week with the back 9 now closed. As you saw last week #11 green complex is in the process of being renovated. The green has been dug out, the drainage and gravel base installed, and the bunkers are being reshaped. As you can see from the pictures the bunkers have been reshaped to resemble the original design and the drainage and bunker liner are being installed this morning. The liner is used on the steep slopes to help hold the sand in place during rain storms. The particular liner we have chosen worked really well in #7 this past summer so we are using the same product. The first loads of greens mix will start to arrive this afternoon and #11 green cavity with be filled and ready for sod by the end of tomorrow. Please check back often during the winter for updates on our progress.